Below are a list of projects AA&C Has handled and executed successfully:

 
 
  1. PROJECT: 2’’ VALVE CHANGE-OUT, VALVE SERVICING&
    STOPAQ WRAPPING ON 6’’ (OLD & NEW)
    DELIVERY LINE AT AWOBA FLOW STATION M/F
    LOCATION: AWOBA
    EXECUTION DATE: 28/03/2013- 30/03/2013
    TERRAIN: SWAMP

    Click here to view the site pictures

  2. PROJECT: REPLACEMENT OF GASKETS, STUD BOLTS &
    NUTS AND VALVE SERVICING AT CAWTHORNE
    CHANNEL II FLOW STATION MANIFOLD
    LOCATION: CAWTHORNE CHANNEL
    EXECUTION DATE: 28/03/2013- 31/03/2013
    TERRAIN: SWAMP

    Click here to view the site pictures

  3. PROJECT: VALVE CHANGE-OUT (10’’, 4’’ & 2’’x600# BLV’s)
    AT EKULAMA II FLOW STATION MF & TIE-IN MF
    LOCATION: EKULAMA
    EXECUTION DATE: 23/12/2012 - 30/12/2012
    TERRAIN: SWAMP

    Click here to view the site pictures

  4. PROJECT TITLE:VALVE CHANGE OUT ON 16’’ALAKIRI/CAWTHORNE
    CHANNEL 11 AGG AT CAWTHORNE CH 11. GAS PLANT
    LOCATION:   CAWTHORNE CHANNEL 11
    EXECUTION DATE: 26/06/2013- 28/06/2013
    TERRAIN:  SWAMP

  5. PROJECT:  RISER COATING REPAIRE USING STOPAQ ON 6’’ 
    KRAKRAMA D/L AT KRAKRAMA F/S  &  M/F
    LOCATION:  KRAKRAMA
    EXECUTION DATE: 22/06/2013- 23/06/2013
    TERRAIN:  SWAMP

  6. PROJECT:  BARREL DOOR CHANGE –OUT
    ON THE 8” CAWTHORNE CHANNEL 111 DELIVERY LINE
    Location: CAWTHORNE CHANNEL111 F/S AND TIE-IN M/F,  
    Execution Date:  28/02/2014 – 06/03/2014    
    TERRAIN:  SWAMP

    Click here to view the site pictures

  7. PROJECT:OIL CLEAN UP AND REMEDIATION SERVICES
    LOCATION: 20 “ OTUMARAESCRAVOS SAGHARA  T/L
    EXECUTION DATE: 03/10/2013 – 14/03/2014
    TERRAIN: SWAMP

    Click here to view the site pictures